| Quyết định | Deadline | CEO | CFO | FP&A | IT/CTO | Credit |
|---|---|---|---|---|---|---|
| Approve IT budget + 2 contractors | Jan 5 | A | C | R | I | I |
| STP threshold calibration | Jan 10 | I | A | C | C | R |
| DSA incentive tier structure | Jan 20 | I | A | R | I | C |
| NPL provision decision | Monthly | I | A | R | I | C |
| Gate 3 Midpoint: Go / Replan | Jun 30 | C | A | R | I | C |
| Monthly MBR report | T+3 hàng tháng | I | A | R | I | C |
EVM Formulas: SV = EV – PV = 37.7 – 41.8 = –4.1 tỷ → BEHIND SCHEDULE CV = EV – AC = 37.7 – 48.2 = –10.5 tỷ → OVER BUDGET EAC = 150.6 / 0.78 = 193.1 tỷ → Overrun 42.5 tỷ nếu không can thiệp TCPI = (BAC–EV)/(BAC–AC) = 1.10 → Cần improve 10% hiệu quả FP&A Action — 3 options cho CFO: 1. Rebalance sang CTV (CAC thấp hơn DSA 40%) → cải thiện CPI 2. Renegotiate DSA commission tier → giảm AC trực tiếp 3. Accept 230K thay vì 250K → giảm provision budget tương ứng
| Workstream | Week N | Week N-1 | Trend | Alert / Action |
|---|---|---|---|---|
| WS1: IT Delivery | AMBER | GREEN | ↓ | STP 28% vs 30% target · Review Sprint 6 |
| WS2: DSA Performance | GREEN | GREEN | → | 1,150 DSA active · 11,200 thẻ/tháng |
| WS3: Partnership | GREEN | AMBER | ↑ | Grab integration resolved ✓ |
| WS4: CTV Network | AMBER | AMBER | ⚠×2 | TUẦN 2 → TỰ ĐỘNG RED TUẦN SAU · Fix App login bug |
| NPL Cohort T1 | GREEN | GREEN | → | 0.8% FPD · Dưới ngưỡng 2% |
| NTC Run Rate | GREEN | GREEN | → | 12,500 thẻ/tháng · Đúng track 250K |
| Ngày | Quyết định | Owner | Revisit |
|---|---|---|---|
| Jan 5 | Approve 14.5 tỷ IT + 2 contractors | CFO | Apr 1 |
| Jan 10 | STP threshold: CIC 650+ · Income 8M+ | Credit Head | Jul 1 |
| Jan 15 | Virtual Card priority over Physical card | CEO | Q2 |
| Jan 20 | DSA commission tier structure | FP&A | Apr 1 |
| Feb 1 | Tier 2 expansion: 8 cities confirmed | Sales Dir | Jun 1 |
| Feb 15 | Partner revenue share: 0.4% standard | CFO | Jul 1 |
| Mar 1 | CTV payout: 150K + 50K activation | FP&A | Jun 1 |
| Jun 30 | Gate 3: Go / Replan / Accept 220K | CFO | Sep 30 |
| Sep 30 | Gate 4 Final sprint decision | CFO | Dec 31 |
| Dec 31 | FY2026 close + Year 2 plan approval | CEO+CFO | Jan 2027 |